State Highway Construction 7/7 to 7/13

The following is a summary of road construction and maintenance scheduled on state highways around Mason County and adjacent areas from July 7, 2019 to July 13, 2019.

Construction

US 101 – Coffee Creek – Remove Fish Barrier
Highway: SR 3 Region: Olympic County: Kitsap Location: Milepost(s) 346.8
Description: Crews will realign a portion of Coffee Creek in order to remove barriers to fish. This project also will rebuild the southbound exit to Shelton-Matlock Road. 
Work Schedule: Crews will soon install orange signs before and after the work zone on Shelton-Matlock Road and West Railroad Avenue. The majority of the work will have little effect on travelers. 

Maintenance

Highway: SR 3 Region: Olympic County: Mason Location: Milepost(s) 19.2 to 20.2
Description: One-way alternating traffic as crews conduct tree trimming under powerlines. 
Work Schedule: 9 a.m. to 2 p.m. each Monday through Thursday through Thursday, Aug. 1. 

Highway: US 101 Region: Olympic County: Mason Location: Milepost(s) 332 to 334
Description: Southbound right shoulder closure for utility work. 
Work Schedule: 11 p.m. Sunday, July 7, until 5 a.m. Monday, July 8.

Highway: US 101 Region: Olympic County: Mason Location: Milepost(s) 347
Description: Shoulder closure in both directions for utility work. 
Work Schedule: 8 a.m. to 4:30 p.m. each weekday from Wednesday, July 10 through Monday, July 15. 

Highway: SR 3 Region: Olympic County: Kitsap Location: Milepost(s) 30 to 50
Description: Intersection and ramp closures as crews refresh crosswalk markings. 
Work Schedule: 8 p.m. Sunday through Wednesday, July 7-10, until 6:30 a.m. each following day. 

Highway: SR 8 Region: Olympic County: Grays Harbor Location: Milepost(s) 0 to 11.5
Description: Single lane closure in both directions for vegetation management. 
Work Schedule: 7:30 a.m. to 3:30 p.m. Thursday, July 11.

Highway: US 101 Region: Olympic County: Jefferson Location: Milepost(s) 283 to 294
Description: Slow moving vehicle for vegetation management. Crews will pull over as needed to let traffic pass. 
Work Schedule: 8 a.m. to 4 p.m. Monday, June 24 through Thursday, Aug. 1.

Highway: US 101 Region: Olympic County: Jefferson Location: Milepost(s) 281 to 295
Description: Right shoulder closure for a mobile sign washing operation.
Work Schedule: 8 a.m. to 4 p.m. Monday, July 8 through Thursday, July 11.   

Special Event

Highway: SR 108 Region: Olympic County: Grays Harbor Location: Milepost(s) 0.8 to 1.4
Description: Total highway closure for the McCleary Bear Festival Parade. A signed detour will be in place. 
Work Schedule: 9 a.m. to 1 p.m. Thursday, July 13. 

Additional Construction

SR 302 – E of Elgin Clifton Rd to SR 16 – Remove Fish Barriers, Paving and ADA Compliance
Highway: 302 Region: Olympic County: Pierce Location: Milepost(s) 10.8 to 16.9
Description: This project removes and replaces three fish barrier culverts under SR 302 with fish passable structures and repaves nearly 7 miles of highway along with ADA improvements for bicyclists and pedestrians.
Work Schedule: During construction, drivers should expect daytime lane and shoulder closures, extended weekend closures, extended on- and off-ramp closures and up to a full, week long closure of the Purdy Spit for deck repairs.  Project webpage.