County Settles Belfair Sewer Construction Dispute

Tuesday, the Mason County Commission approved a settlement with Boss Construction over the cost of constructing a portion of the Belfair Wastewater Reclamation Facility. Brian Matthews, Director of Public Works for the County, explains:

The settlement amount is ten cents less than $1.2 Million ($1,199,999.90) and allows the County to close out the $54 Million project. Disputes like this are not uncommon for construction projects of this magnitude but Commissioner Randy Neatherlin believes the County didn’t owe additional money: